New materialsEngineering plastic substitution and cost reduction
Two domestic material routes evaluated and one put into trial production, without changing the existing mould or assembly interface.
Key parameters fixed through range trials and written into working documents, narrowing yield variation between shifts.

The customer's new product entered trial production and yield varied clearly between shifts. Operators adjusted parameters by experience, so problems were hard to reproduce.
Before ramping to volume production, the customer wanted a stable parameter range and clarity on which parameters must not be adjusted on the floor.
Yield differences between shifts narrowed clearly, and anomalies could be traced to specific parameters.
Floor adjustments were limited to confirmed ranges, reducing experiential trial and error.
Trial parameters and inspection requirements became a document that can move directly into production preparation.
Recorded adjustable parameters and adjustments during trial production, and identified the items most correlated with defects.
Ran small orthogonal parameter trials to confirm the usable range of each parameter and their interaction.
Set yield-critical parameters as controlled items while keeping reasonable adjustment space for the rest.
Wrote the confirmed parameter ranges into trial work instructions with first-article confirmation and patrol requirements.